Latest on Mountain Parkway Expansion

 

Salyersville
Restaurant Row
Crews have made significant progress in relocating utilities and building a bridge over Burning Fork on the western end of this 2.57-mile segment.

Workers recently placed six beams on the new bridge, and three more large beams will be added later this month.

A culvert on an access road on the north side of the project has been completed. Construction also continues on two large culverts on the east end of this section.

Clearing work has begun at various locations throughout this segment.

Construction is not expected to affect traffic, but the speed limit in the area has been reduced for the safety of workers and travelers.
Magoffin County
Construction crews continue to mark and fence the right of way for the modernized KY 30 interchange.

Meanwhile, crews working on the KY 7 interchange have poured nearly 950 cubic yards of concrete in the past three weeks while building the bridge deck over the Licking River.

Clearing and excavation activities will resume in the spring.

The Magoffin County Central Segment of the Mountain Parkway Expansion runs from just west of mile point 70 to just east of mile point 75.

The speed limit in the area has been reduced, and traffic on the parkway may be slowed or stopped periodically for the safety of workers and travelers.
Morgan County
Crews have been moving dirt and clearing trees along the Magoffin-Morgan County line to prepare to widen this 8.2-mile section of the Mountain Parkway.

Utility relocation continues ahead of road construction, and workers will begin relocating water lines on Thursday, March 9.

No traffic impacts are expected on the parkway. Traffic on KY 205 will be affected minimally, if at all.

The Morgan County segment of the project runs from just west of Exit 57 near Helechawa to just west of the Cutino-Hager Road overpass. In addition to widening the parkway to four lanes, crews will improve two existing interchanges and reconstruct an ā€œSā€ curve near the county line to improve safety and mobility.

 

About the Mountain Parkway Expansion
The Mountain Parkway Expansion is a 46-mile transportation improvement project that will create a wider, safer connection between Eastern Kentucky and the rest of the Commonwealth. It is a key transportation project designed to close the only gap in a 400-mile, four-lane, high-speed corridor for commerce and mobility across Kentucky from Pikeville to Paducah. The project will widen 30 miles of the existing parkway to four lanes and extend the parkway by about 16 miles between Salyersville and Prestonsburg.

For additional information, go to www.mtnparkway.com. Project updates may also be found on Facebook and Twitter. A project office is open in Magoffin Plaza in Salyersville; call (606) 349-8160 for hours.